Work is starting downstream of the CNC – how were the designs decided?

Update: I’ve been closely following the issues around the Christchurch Northern Corridor (CNC) for some time now. The motorway is due to open ‘mid 2020’, and work is getting underway in the St Albans, Edgeware, and Mairehau areas to to manage the expected downstream increase in traffic.  This article recaps the Christchurch City Council’s consultation and decision-making processes over the past two years.

DEMP consultation leaflet 1
The leaflet from the first of three rounds of consultation

The Downstream Effects Management Plan (DEMP) was commissioned by the Christchurch City Council Continue reading “Work is starting downstream of the CNC – how were the designs decided?”